Friday, December 2, 2011

This project is nearing completion with only punch list work remaining.

Monday, November 21, 2011

Arrow Road Construction has completed the surface course of asphalt on Glenview Road. The striping contractor will be installing thermoplastic pavement striping this week, with raised reflective pavement markings to be installed later in the week as well. After the pavement striping is complete all that remains is landscaping and punchlist!

Thursday, November 3, 2011

Arrow Road Construction has completed the first layer of asphalt, the level binder this week. The underground contractor is scheduled to begin structure adjustments within the pavement early next week. Arrow Road Construction is then scheduled to begin the final asphalt layer, the surface course, late next week or early the following week.

Friday, October 28, 2011

The contractor is working grinding the existing pavement surface this week. Next week, the concrete contractor, Lampignano is scheduled to resume curb and gutter replacement. Following the curb and gutter replacement, the asphalt contractor will begin the first lift of asphalt installation late next week(weather permitting).

Friday, October 14, 2011

Arrow Road Construction is scheduled to complete asphalt patches early next week. Then AT&T will complete utility structure adjustments. Following AT&T the concrete contractor, Lampignano is scheduled to complete curb and gutter replacement. Late next week, Arrow Road Construction will begin grinding Glenview Road in preparation for asphalt paving.

Friday, October 7, 2011

The utility contractor, DeVinci Construction, Inc. is scheduled to continue utility work in various locations onsite. The concrete contractor, Lampignano is scheduled to resume curb and gutter replacement next week along Glenview Road.

Friday, September 30, 2011

The concrete contractor, Lampignano will continue with curb and gutter replacement this week on the north side of Glenview Road. The utility contractor, DeVinci Construction, Inc. is scheduled to continue utility work next week in various locations onsite.